How many power meters are required to be installed under the Green Mark  pre-requisite for permanent M&V instrumentation?

Turning energy savings into profits!

How many power meters are required to be installed under the Green Mark pre-requisite for permanent M&V instrumentation?

A minimum of four (4) power meters are required for each of the following groups of equipment:

  • Chiller(s),
  • Chilled water pump(s),
  • Cooling Tower(s), and
  • Condenser water pump(s).

 