How many power meters are required to be installed under the Green Mark pre-requisite for permanent M&V instrumentation?
A minimum of four (4) power meters are required for each of the following groups of equipment:
- Chiller(s),
- Chilled water pump(s),
- Cooling Tower(s), and
- Condenser water pump(s).